Example of a flood management scheme in the Uk
- Created by: Drageemily
- Created on: 23-01-19 17:49
View mindmap
- Banbury Floods
- Costs and benefits
- Quality of life improved. A361 no longer closed. Cost £18.5m but benefits over £100m.
- Small reservoir created from earth taken for embankment. Floodplain protected for flooding
- Impacts
- 2007: Impacts were repeated after rived burst its banks after heavy rainfall.
- 1998: flooding led to closure of railway. caused £12.5m damage. More than 150 homes and businesses were affected.
- Prevention methods
- A361 raised and drainage below road improved. Earth embankments built. Floodwalls built.
- Pumping station to transfer excess water. Creation of new Biodiversity Action Plan to allow nature to 'soak' up excess water
- Located in Cotswold Hills, north of Oxford.
- Costs and benefits