Project Management Test
- Created by: Ade4568
- Created on: 03-05-19 13:32
Other questions in this quiz
2. A project has a critical path of 21 days. The "testing the solution" task has a slacktime of three days. What is the minimum time the project can be completed
- 24 Days
- Depends whether "testing the solution" is on the critical path
- 21 Days
- 18 Days
3. What environment does the recognised project methodology covered in this module assume?
- A third party environment
- A customer/ Supplier environment
- A specialist environment
- A fixed-price contract
4. The process, Directing a Project begins when?
- Before start up of the project
- From starting up a project
- At the end of the initiation stage
- After the start up of the project
5. It would be chaotic to have the people who are working on the project starting activities whenever they think fit. What product does the recognised project methodology covered in this module use to control this?
- Checkpoint report
- Work Package
- Project issue
- Risk Log
Comments