Performance and Breach cases

?
What general rule was established in Moore v Landauer?
Performance must be exactly according to the terms of the contract
1 of 13
In what case was the statement “If a shoemaker agrees to make a pair of shoes, he cannot offer you one shoe and ask you to pay half the price.” made?
Re Hall & Barker
2 of 13
What rule is included in Cutter v Powell?
Entire contract rule
3 of 13
What is the rule applied in Viger v Cook?
Entire contract rule
4 of 13
What is the rule applied in Bolton v Mahadeva?
Entire contract rule
5 of 13
What is the rule in Sumpter v Hedges?
Partial performance entitles party to payment for work done, if partial performance is accepted by the other party
6 of 13
What rule is applied in Planché v Colburn?
Where the promisor prevents full performance, the claimant is entitled to paymnet for the work they have completed
7 of 13
Boone v Eyre applies what principle?
Substantial performance
8 of 13
What principle was applied in Hoenig v Isaacs?
Substantial performance
9 of 13
Startup v Macdonald - what principle was applied here?
Entire contract
10 of 13
The Hochster v. De la Tour case involved what principle?
Breach by anticipatory repudiation
11 of 13
White & Carter v McGregor applied what principle?
Affirming the contract after repudiatory breach
12 of 13
What principle was applied in Avery v. Bowden?
Affirmation of repudiation
13 of 13

Other cards in this set

Card 2

Front

In what case was the statement “If a shoemaker agrees to make a pair of shoes, he cannot offer you one shoe and ask you to pay half the price.” made?

Back

Re Hall & Barker

Card 3

Front

What rule is included in Cutter v Powell?

Back

Preview of the front of card 3

Card 4

Front

What is the rule applied in Viger v Cook?

Back

Preview of the front of card 4

Card 5

Front

What is the rule applied in Bolton v Mahadeva?

Back

Preview of the front of card 5
View more cards

Comments

No comments have yet been made

Similar Law resources:

See all Law resources »See all Contract resources »