More cards in this set

Card 6

Front

Once practical completion is achieved… * the employer is able to take possession of the works; * the employer’s right to instruct.....

Back

Preview of the front of card 6

Card 7

Front

JCT Contracts can be amended to specify PC, however it'll have to be left to the discretion of the....

Back

Preview of the front of card 7

Card 8

Front

NEC3 contracts provide more clarity by using the term “Completion”, which is defined as occurring when the contractor has done all the work the works information in the contract requires him to do by the completion date, and....

Back

Preview of the front of card 8

Card 9

Front

'PC' can be detrimental to the contractor as failure to comply with one or more conditions, no matter how minor, can allow the employer to legitimately refuse to...

Back

Preview of the front of card 9

Card 10

Front

A contract which contains conditions precedent to practical completion should be reviewed carefully by the contractor, who must ensure that....

Back

Preview of the front of card 10

Card 11

Front

practical completion cannot be certified because the contractor has left administrative matters such as the signing of collateral warranties and the preparation of operation....

Back

Preview of the front of card 11