The node number, based upon the order in which it is drawn.
1 of 10
Earliest start time (EST)
The earliest the following activity can possibly start.
2 of 10
Latest finish time (LFT)
The latest an activity can finish without delaying the whole project.
3 of 10
Duration
The activity duration is shown below the line
4 of 10
Node 1
Node 1 always starts at 0. Node 1 will always have an EST of 0 and an LFT of 0.
5 of 10
EST
EST is calculated from left to right by adding the duration of the activity to the previous EST. When two or more activities go into the same node the highest number goes in the EST section.
6 of 10
LFT
The LFT of the final node always matches the EST. To complete the LFT you calculate from right to left.When two or more activities go into the same node the lowest number goes in the LFT section.
7 of 10
Float time
LFT – duration – EST
8 of 10
Advantages
Shortens the overall time of a project,Improves focus on project, Greater productive efficiency, Allows for just in time
9 of 10
Disadvatages
Relies on estimations,Does not take into account external influences, Large projects can be too complex for CPA,Is only a starting point for a successful project
10 of 10
Other cards in this set
Card 2
Front
The earliest the following activity can possibly start.
Back
Earliest start time (EST)
Card 3
Front
The latest an activity can finish without delaying the whole project.
Back
Card 4
Front
The activity duration is shown below the line
Back
Card 5
Front
Node 1 always starts at 0. Node 1 will always have an EST of 0 and an LFT of 0.