More cards in this set

Card 6

Front

The amount of time that non-crucial activities within a project can be delayed without affecting the deadline for completion of the project as a whole.

Back

Preview of the front of card 6

Card 7

Front

The number of days that an activity can be delayed without delaying the project, measured by the formula: LFT-EST-duration of the activity

Back

Preview of the front of card 7

Card 8

Front

What does LFT stand for?

Back

Preview of the front of card 8

Card 9

Front

What does EST stand for?

Back

Preview of the front of card 9

Card 10

Front

Production based on the range of waste-saving measures inspired by Japanese manufacuring companies.

Back

Preview of the front of card 10

Card 11

Front

A Japanese philosophy that organises operations so that items of stock (inventory) arrive just at the time they are needed for production or sale. The ultimate aim is to eliminate the need for stock, although in practice this is not always ideal.

Back

Preview of the front of card 11

Card 12

Front

Shorthand forJust-in-time systems.

Back

Preview of the front of card 12

Card 13

Front

A policy of implementing small, incremental changes in order to achieve better quality and/ or greater efficiency. These changes are invariably suggested by employees.

Back

Preview of the front of card 13

Card 14

Front

Another term to describe Kaizen.

Back

Preview of the front of card 14