D1 Definitions - Critical Path

?
  • Created by: Cam
  • Created on: 21-05-15 18:17
Early Event Time
Earliest arrival at an event that allow all previous events to be completed.
1 of 5
Late Event Time
The latest an event can be left without delaying a project.
2 of 5
Critical Activity
An activity where any increase in its duration will result in an increase in the overall project duration (i.e. float of 0).
3 of 5
Critical Path
Path from source node to sink node that follows exclusively critical activities - the longest path in a network.
4 of 5
Total Float
Amount of time an activity can be delayed without affecting the total project duration.
5 of 5

Other cards in this set

Card 2

Front

The latest an event can be left without delaying a project.

Back

Late Event Time

Card 3

Front

An activity where any increase in its duration will result in an increase in the overall project duration (i.e. float of 0).

Back

Preview of the back of card 3

Card 4

Front

Path from source node to sink node that follows exclusively critical activities - the longest path in a network.

Back

Preview of the back of card 4

Card 5

Front

Amount of time an activity can be delayed without affecting the total project duration.

Back

Preview of the back of card 5

Comments

No comments have yet been made

Similar Mathematics resources:

See all Mathematics resources »See all Networks, algorithms and problem solving resources »