Critical Path 0.0 / 5 ? Business StudiesN/AA2/A-levelWJEC Created by: Joebarlow_10Created on: 07-03-19 20:43 Activity A part of a project that requires time and resources. Represented by an arrow left to right. 1 of 8 Earliest Start Time Shows the Earliest time at which the following activities can be started. 2 of 8 Latest Finish Time Shows the time by which an activity must be finished. 3 of 8 The critical Path Is made up of Activities which take the longest to complete- they determine the whole length of the project. 4 of 8 Total Float Measures the spare time available for an activity. 5 of 8 Total Float Time Formula LFT - duration - EST 6 of 8 Free Float Measures the spare time available so the is no delay to the next activity. 7 of 8 Free Float Formula EST (next activity - duration - EST (this activity) 8 of 8