Construction Design Management Regs 2015

?
When are the works notifiable?
30 days and more than 20 workers on site at any one point or more than 500 person days
1 of 12
What are the clients responsibilities?
Appoint other duty holders, notify the HSE if necessary, ensure construction phase plan is in place before work starts,sufficient time and resourses, relevant info to other duty holders, Principal designer and contractors do their duty, welfare facil
2 of 12
Designers Must?
Eliminate or control risks and future maintenance work, provide info to other duty holders, info for H and S file if more than one contractor.
3 of 12
Principal designers must?
Appointed if more than one contractor, plan, manage,monitor and co ordinate H and S in the pre construction phase. Advise and assist client. prepare pre cons info and pass on.co ordinate H and S of design.
4 of 12
Principal designers cont....
Manage communicaion bewteen Client, Principal contractor, desgner/s.Liaise with Principal contractor on on going, prepare/update H and S file, pass H and S file onto client.
5 of 12
Principal contractor?
Plan, manage and monitor the construction phase of the build,Prepare, develop and implement the construction phase plan, Check competence of contractors, Workers have induction, receive training of req, welfare facilities, consult workers
6 of 12
Principal contractor cont.............
liaise with Principal designer, secure site.
7 of 12
Contractors Must?
Plan,monitor their own work and that of others, check competance of all parties and workers,train employees and info, run a clean safe site. more than 1 contractor then liaise with PD. if 1 contractor then CPP
8 of 12
Workers must?
check own competance, co operate with others, report obvious risks, work safely and within the law.
9 of 12
Pre Construction info?
Principal designer with help of the client provides H and S info for people quoting for the works.
10 of 12
Construction Phase Plan
Principal contractor supplies this or contractor if single contractor, client must not let the work start until in place,detailed plan explaining how to do the job safely.
11 of 12
H and S file
Maintenance manual, principal designer puts together and client maintains,Info for client to maintain, refurbish, renovate the building in the future. Only req if more than one contractor on the job.
12 of 12

Other cards in this set

Card 2

Front

What are the clients responsibilities?

Back

Appoint other duty holders, notify the HSE if necessary, ensure construction phase plan is in place before work starts,sufficient time and resourses, relevant info to other duty holders, Principal designer and contractors do their duty, welfare facil

Card 3

Front

Designers Must?

Back

Preview of the front of card 3

Card 4

Front

Principal designers must?

Back

Preview of the front of card 4

Card 5

Front

Principal designers cont....

Back

Preview of the front of card 5
View more cards

Comments

No comments have yet been made

Similar All resources:

See all All resources »See all NEBOSH resources »